Poor contracting at MoD leaves taxpayer to shoulder ballooning costs

Posted by Hazel Duhy on in UK News.

In a report published today, Wednesday 13 May 2020, the UK Parliament’s Public Accounts Committee says the Ministry of Defence has left the taxpayer to shoulder huge cost increases due to the MoD’s poor contract design and management. 

The MoD said it “immensely regretted” the huge waste of taxpayers’ money, which was caused by poor management of three nuclear infrastructure projects, resulting in a combined cost increase of £1.35 billion and with delays of between 1.7 and 6.3 years. 