New Sellafield radioactive waste handling facility planned

EARLY work on a new radioactive waste handling facility at Sellafield could begin in 2029 under proposals submitted to Cumberland Council.

The Sludge Handling and Export Plant (SHEP) would handle an estimated 1,500 cubic metres of radioactive sludge recovered from one of the nuclear site's oldest facilities.

The project is at an early feasibility stage and has yet to be fully developed or approved, with the proposed facility expected to begin operations around 2040.

Sellafield Ltd has submitted a request for an Environmental Impact Assessment (EIA) screening opinion to establish whether the development requires a full environmental assessment.

The new building would measure approximately 47 metres long, 28 metres wide and 21 metres high, occupying a footprint of around 1,300 square metres.

It would be built alongside the existing Sludge Packaging Plant 1 (SPP1), which currently provides temporary storage for material recovered from the First Generation Magnox Storage Pond.

The open-air pond, constructed during the 1950s and 1960s, was originally used to receive and store irradiated nuclear fuel and remove its cladding before processing.

Over decades, radioactive sludge accumulated in the pond and must be safely removed and managed as part of the site's decommissioning programme.

The proposed new facility would receive sludge from SPP1 through connecting pipelines, increase its concentration by allowing solids to settle and removing liquid, and transfer the material into 500-litre drums.

These would then be transported to the Waste Encapsulation Plant for further treatment before being placed in interim storage elsewhere on the Sellafield site.

A Sellafield Ltd spokesman said: "Our purpose is to create a clean, safe, and secure environment for future generations.

"Designing and building the next generation of treatment, packaging, and storage facilities to manage waste from our historic facilities is an important part of this.

"The Sludge Handling and Export Plant (SHEP) is intended to play a crucial role in our hazard and risk reduction work by helping to manage waste products retrieved from our legacy ponds."

Construction could begin in 2034

The project is currently expected to take approximately ten years to deliver, including design, enabling works, construction, commissioning and regulatory assurance.

Early enabling works could begin in 2029 alongside the final design process, with major construction activities expected approximately five years later.

The building would then undergo testing and commissioning before entering service, although all timescales remain indicative.

Up to 200 construction workers could be required each day, with around half expected to be drawn from the existing Sellafield workforce.

Once operational, approximately 85 staff would work across five shifts, using existing personnel rather than creating additional posts.

The facility is expected to handle around 600 drums of waste annually, with sludge handling and export operations anticipated to continue for approximately seven years.

Environmental assessment sought

The screening request argues that the proposed development would not have significant adverse environmental effects.

Although the facility would concentrate and transfer radioactive sludge, it would not carry out treatment processes that change the nature of the waste.

The submission states: "Overall, the project is expected to have a long term positive environmental impact in that it will facilitate hazard and risk reduction on the Sellafield Site."

The Office for Nuclear Regulation has told Cumberland Council it "does not advise against this development", while the Joint Emergency Management and Resilience Team has raised no comments on the proposals.

Cumberland Council's highways officers have identified no likely significant environmental effects on the road network, but have requested that any future planning application include a construction traffic management plan, particularly addressing vehicle movements on the A595.

The council's flood authority has also identified no likely significant environmental effects, although it has requested further details of construction drainage arrangements should a planning application be submitted.

Cumberland Council has yet to issue its screening opinion.

The request, reference SCR-4/26/58, represents a preliminary stage in the planning process rather than an application for permission to construct the facility.